EKO ELECTRICITY DISTRIBUTION COMPANY (EKEDC)
PUBLIC NOTICE
INVITATION FOR THE PRE-QUALIFICATION OF CONTRACTORS FOR 132/33KV TRANSMISSION LINES & SUBSTATIONS REHABILITATION PROJECTS AND EQUIPMENT SUPPLY
1. INTRODUCTION
The Eko Electricity Distribution Company (EKEDC) has received a CREDIT facility from the Central Bank of Nigeria (CBN) for Accelerated Transmission – Distribution Interface Projects to invest in the Transmission Company of Nigeria (TCN)’s rehabilitation and expansion projects.
2. SCOPE OF WORKS
(A) LOT/EKEDC/SS/1
Akoka 1X40MVA4 1x4SMVATS:
(i) Upgrading of 1X40MVA & 1x45MVA with 2x60MVA, 132/33kV Power Transformer at Akoka TS.
(ii) Construction of additional 33kV feeder bay.
(iii) Conversion of indoor Circuit breaker to outdoor.
(B) LOT/EKEDC/SS/2
Isolo TS 1X45MVA, 2X60MVA, 132/33kV TS:
(i) Replacement of faulty 60MVA 132/33kV Transformer.
(ii) Installation of 3nos 33kVA Feeder bays.
(C) LOT/EKEDC/SS/3
Itire TS 1X30MVA, 1X40MVA & 1x60MVA 132/33kV:
Replacement of failed 60MVA transformer at Itire TS.
(D) LOT/EKEDC/SS/4
Ojo TS 2 X 60MVA, 132/33kV TS
(i) Construct 3nos 33kV bays at the transmission station.
(ii) Rehabilitation of problematic indoor circuit breakers -(Elimson -Turkey type)- Faulty 33kv panel to be replaced for System Reliability.
(E) LOT/EKEDC/SS/5
Lekki TS 2X60MVA, 132/33kV TS
(i) Installation of additional 60MVA, 132/33kV transformer, and circuit breaker.
(ii) Installation of additional 33kV indoor breaker.
(F) LOT/EKEDC/SS/A
Agbara TS 2X40MVA, 132/33kV TS
(i) Upgrading of 2x45MVA with 2x100MVA, 132/33kV Transformers.
(ii) Construction of additional 2x33kv feeder bays.
(G) LOT/EKEDC/SS/7
Ajah 1x100MVA, 2 X60MVA, 1X60MVA Mobitra 132/33kV Transmission S/S:
(i) Installation of 1x100MVA, 132/33kV Transformers at Aja TS.
(ii) Construction of additional outdoor 3x33kv feeder bays.
(H) LOT/EKEDC/SS/8
Apapa Road 1X45MVA, 132/33kV TS:
(i) Construction of additional 33kV feeder boys.
(ii) Installation of additional lx45MVA, 132/33kV Mobitra at Apapa Rd TS.
(I) LOT/EKEDC/SS/9
Eko Atlantic City Transmission Line
Engineering Design, Procurement, Construction and Commissioning of 132kV Double Circuit Transmission line from Lekki Substation to the proposed 132/33kV Atlantic City proposed substation on Steel Poles towers with pile foundations.
(J) LOT/EKEDC/SS/10
Eko Atlantic City Transmission Substation
Engineering Design, Procurement, Construction and Commissioning of 2X60MVA 132/33kV Eko Atlantic City GIS Substation.
(K) LOT/EKEDC/SS/11
Transformers Spares:
(i) Power Transformers (2x150MVA + 2X100MVA +2x60MVA).
(ii) Mobitra; 1x60MVA.
3. ELIGIBILITY REQUIREMENTS (NIGERIAN COMPANIES ONLY)
Suitable Nigerian companies are invited to participate in the pre-qualification exercise by submitting the following pre-requisite requirements:
(a) Certificate of incorporation with the Corporate Affairs Commission (CAC) in Nigeria with forms C02 and C07.
(b) Current Tax Clearance Certificate for the post three years valid till 2021.
(c) Three years company audited financial statement for the period of 2018 -2020 duly stamped by a registered audit firm.
(d) PENCOM Compliance Certificate valid till 31st December, 2021.
(e) Industrial Training Fund (ITF) compliance certificate Valid till 31st December, 2021.
(f) Nigeria Social Insurance Trust Fund (NSITF) compliance certificate valid till 2021.
(g) NEMSA Compliance Certificate for 2021.
For Joint Venture Partnerships, the Joint Venture Agreements must be signed by all the parties, a copy of which must be attached, in addition, all partners must meet the above requirements.
You need to be logged in to view the rest of the content. Please
Log In. Not a Member?
Join Us